Terminal 2 time exntension ends Monday
The four-month time extension granted by Tocumen SA, to the Odebrecht construction company to complete the construction of the airport’s new passenger terminal, runs out on Monday, September 30.
The extension is part of the fifth addendum that the airport signed with the Brazilian company at the end of May.
The agreed addendum is added to the one signed at the beginning of the year for $25 million d and that raised the cost of the project that initially agreed at $679.4 million to $917 million
Among the works that Odebrecht had to finish – as agreed in the fifth addendum – is the baggage, fire extinguishing system, among others, reports La Prensa.