IN AN UNPRECEDENTED frenzy of construction, the last government contracted at least $1.9 billion in projects, many of them awarded under the umbrella of the Ministry of Public Works.
According to the first audits carried out by the Comptroller General of the Republic, five of these works had a possible overrun of $318 million. These five Contracts do not reach 10% of the total works awarded in the previous government. This indicates the dimensions the entire iceberg of corruption and robbery suffered by the country. We now need to
We now need to support the Attorney General’s Office to recover these funds. We must demand that all works be audited in order to eliminate the criminal contractors and political party organizations who assault the treasury and steal the property of all Panamanians.