Metro line 2 27 percent advanced
AFTER 13 months of construction work Metro line 2 is 27 percent advanced, and 12 of the 16 stations on the line are underway says Metro Director Roberto Roy. Agustín Arias, Metro Director of projects and planning said that, to date, the agency has been able to optimize the location of stations and access to them. All the stations are supposed to be completed by the end of next year. The Metro also plans to expand the trains on line 1 from three to five cars. This will increase the capacity of each train to 600.
Line 3 schedule
October 22, 2016: Interested company prequalification called
December 6, 2016: Visit to the site
December 7, 2016: Approval meeting
February 15, 2017: Receipt of prequalification proposals
Late 2017 to early 2018: Start of the construction phase
Period of execution: four years
Late 2021 Conclusion of works
2022, Entered into operations